How Should a Rooftop PV Crew Stage Modules on an Existing Factory Roof?
A lightweight module can reduce the weight of the installed modules, but pallets, handling equipment and crews may all occupy the same small part of a roof during construction. Include those temporary loads in the engineering review. The weight of one module cannot establish how much an existing roof can hold at a staging point.
Before delivery, mark the ground holding area, the lift landing point, the roof distribution route and the approved staging areas on one current roof plan. Show rooflights, drains and the access routes that must remain open. Match each delivery batch to the installation area that will use it, and identify which materials can go to the roof and which should remain on the ground.
If the packaging, delivery sequence or lifting point changes, record it and review the agreed plan. Use the loads, locations and roof protection measures approved for the project.